# Iowa RRNC Radon Code for New Homes | Builder Guide

> Iowa HF 2297 requires passive radon systems in new homes from July 2026. The RRNC build sequence, inspection points, activation and pre-closing testing.

URL: https://iowaradonsystems.com/guide/iowa-rrnc-new-home-radon-code/
Last-Modified: 2026-10-10
Tags: radon resistant new construction iowa

Radon Guide // Commercial Radon Services for Builders, Schools and Multifamily

# Radon-Resistant New Construction in Iowa: A Builder's Guide

Iowa HF 2297 requires passive radon systems in new homes from July 2026. The RRNC build sequence, inspection points, activation and pre-closing testing.

Updated October 10, 2026 6 min read By the Radon Systems of Iowa team

![New-construction basement with a gravel base and plastic membrane before the slab pour](https://placehold.co/1200x630/0b2545/ffffff?text=New+construction+Iowa+basement+with+gravel+base+and+plastic+membrane+laid+before+concrete+slab+pour)

Iowa now requires radon control in new homes. Under House File 2297, every new single-family and two-family residence permitted from July 1, 2026 must include a passive radon system built to the 2021 International Residential Code, Appendix AF. For builders, that turns radon from an optional upgrade into a standard part of the schedule. This guide lays out the build sequence in the order it happens on site, with the inspection points that tend to trip crews up.

> **Check your local code**
> 
> HF 2297 sets the statewide baseline. Inspection steps and paperwork can still differ between jurisdictions. Confirm the process with each building department before the first pour.

## Why It Pays to Build It In

Installing radon-resistant features during construction typically costs a few hundred dollars per home. Retrofitting the same house later commonly runs $1,200 or more. In fast-growing metro suburbs like Altoona, where subdivisions from builders such as Hubbell Homes, D.R. Horton and Jerry’s Homes are adding houses quickly, a clean RRNC process also prevents radon surprises from stalling closings.

## The Build Sequence

### Stage 1: Before the slab (excavation and footings)

-   Plan the vent stack route now. Choose an interior wall chase that runs straight to the attic.
-   Avoid exterior walls. A stack in a cold wall can freeze in an Iowa January and chokes off the draft.

### Stage 2: Gas-permeable layer

Place a 4-inch layer of clean, coarse aggregate under the slab, or an approved soil gas mat where gravel is impractical. The goal is a continuous layer that lets soil gas move freely to the collection point.

### Stage 3: Collection point and riser

Set a T-fitting or perforated collection pipe in the gravel layer and stub a 3 or 4 inch Schedule 40 PVC riser up through where the slab will be.

### Stage 4: Membrane

Lay polyethylene over the aggregate, at least 6-mil, with seams overlapped and taped. **Inspection point:** this is where membranes get torn by boots and wheelbarrows. Walk it and tape every tear before the pour.

### Stage 5: Pour and seal

Pour the slab. Seal control joints, the slab perimeter and every plumbing and utility penetration with polyurethane sealant once the concrete has cured enough. Install a gasketed, bolted sump lid with a viewing port.

### Stage 6: Vent stack and labeling

Run the stack through the interior chase to the attic and out the roof. Label the pipe on every level so no future plumber mistakes it for a drain.

![Framed house with a radon vent stack through the roof, builders on site](https://placehold.co/800x500/0b2545/ffffff?text=Framed+new+house+with+radon+vent+stack+running+through+roof+and+builders+working+on+site+in+Iowa+subdivision)

### Stage 7: Fan-ready attic

Leave clear space around the stack in the attic and have the electrician install a junction box nearby. Skipping this step is the single most expensive RRNC mistake, because it multiplies activation labor later.

| Stage | Inspection point | Common miss |
| --- | --- | --- |
| Aggregate | Continuous, clean, correct depth | Fines or gaps |
| Membrane | Overlapped and taped seams | Torn during the pour |
| Sealing | Joints and penetrations caulked | Utility chases left open |
| Sump | Gasketed, bolted lid | Open crock |
| Stack | Interior chase, labeled | Routed up an exterior wall |
| Attic | Clearance and a junction box | No power for a future fan |

## After Drywall: Test Before Closing

Once the home is enclosed, HVAC is running and drywall is done, run a short-term test on the lowest livable level under closed-house conditions.

![Technician running a pre-occupancy radon test in a new basement](https://placehold.co/800x500/f4f8f8/0b2545?text=Radon+technician+running+pre+occupancy+radon+test+in+finished+new+construction+basement+before+homeowners+move+in)

A passive stack alone often does not get a Central Iowa basement below 4.0 pCi/L. Polk County averages are reported around 7.3 to 9.2 pCi/L, and fresh slabs in new subdivisions commonly develop micro-cracks as the soil settles. Our guide to 

passive vs. active systems

[/guide/passive-radon-pipe-vs-active-fan/ →](/guide/passive-radon-pipe-vs-active-fan/)

 covers the performance difference.

## Activating the Stack

If the test is high, or if you choose to deliver every home active, activation is short work on a well-built rough-in:

1.  Mount a continuous-duty inline fan on the attic stack.
2.  Wire it to the junction box.
3.  Add a U-tube manometer on the basement riser.
4.  Label the system and confirm suction.
5.  Run a 48-hour clearance test.

Some builders activate by default; others test first. Both are reasonable, and a documented result is a selling point either way.

## Working With Builders and Developers

Radon Systems of Iowa supports builders across the east metro with:

-   **Pre-pour consultation** on aggregate, membrane and stack routing.
-   **Mid-build checks** before the slab and before drywall.
-   **Pre-occupancy testing** on single homes or whole phases.
-   **Passive-to-active upgrades** when results call for it.
-   **Multifamily coordination**, including lender-driven work. See 
    
    HUD radon requirements
    
    [/guide/hud-multifamily-radon-testing-iowa/ →](/guide/hud-multifamily-radon-testing-iowa/)
    
    .

Send your plans and build schedule through our 

new construction radon services

[/commercial-services/ →](/commercial-services/)

 page for a project-based estimate on your next Altoona or Polk County subdivision.

Quick Answers

## Frequently Asked Questions

Does Iowa require radon-resistant construction in new homes?

Yes. Iowa House File 2297 requires newly constructed single-family and two-family homes to include a passive radon mitigation system, effective July 1, 2026, following the 2021 IRC Appendix AF. Confirm inspection procedures with the local building department in each community you build in.

When should a builder activate the passive stack?

When a pre-occupancy or later test shows radon at or above the EPA action level of 4.0 pCi/L, or by default if the builder chooses to deliver every home active. Activation means adding an inline fan, power, a manometer and labels to the existing stack.

Do you work with builders on multiple homes or whole subdivisions?

Yes. We provide pre-pour guidance, mid-build checks, pre-occupancy testing and passive stack activation for builders and developers, with project-based pricing for multi-home work.

Related Service

## Commercial Radon Services for Builders, Schools and Multifamily

Commercial radon mitigation in Altoona and Polk County for new construction, HUD-financed multifamily properties, schools, childcare centers and large-slab commercial buildings.